Sometime in the week ending August 21, crews at Eliot Street pulled the first of the steel sheet piles that had held back the water since 2023. Seawater from Marine Stadium and Alamitos Bay started moving through an open channel into Colorado Lagoon. The area was first closed to cars and pedestrians in November 2022. The water got its route back weeks before the neighborhood got its streets and paths. What East Long Beach gets back this fall arrives in pieces, in an order the City has largely spelled out. Only the final piece has no date.
The Biggest Change Happened Underwater
For decades, the 18-acre lagoon at 5119 East Colorado Street connected to Alamitos Bay through a 900-foot underground concrete box culvert under Marina Vista Park. The culvert went in during the 1960s as development spread around the lagoon. It never let the tides drain fully, and storm drains emptying into the lagoon made the pollution worse. By the late 1990s, Heal the Bay was regularly naming the lagoon a "Beach Bummer," one of the most polluted water bodies in the state. This is the same water where the 1928 U.S. Olympic diving trials were held.
This summer's work took that culvert out. In July 2026, the City shut down the connection between the bay and the lagoon. Crews ran aerators while consultants monitored the water, and the old box culvert was demolished in August. Then cranes set up at Larry Curtis Park and Alamitos Heights Park to lift out the sheet piles. Once the first piles came out at Eliot Street, the open channel was live. The City calls it a major milestone toward the vision in the 2005 Master Restoration Plan. By early September, every sheet pile segment was out except one damaged piece.
Friends of Colorado Lagoon formed in 2001 to push for this. The channel was the last major phase. On the surface, the big moment looked like a crane at a neighborhood park on a summer weekday.
Colorado Street Came Back First, and the Fire Station Is Why
The first piece above water is the one most of the neighborhood drives. Paving on Colorado Street and parts of Eliot Street started September 18, and final striping was done the week of September 25. The City planned to reopen Colorado Street on September 30, mainly to restore access in and out of Fire Station 14. Longbeachize confirmed on October 1 that cars and bikes could get through again, crossing a new bridge over the channel.
That restores a shortcut commuters have been missing. Colorado Street lets drivers reach Pacific Coast Highway or Studebaker by way of Loynes Drive and skip 7th Street. The streets had last been promised for the end of 2024, before asbestos turned up and pushed the schedule back again.
Expect the drive to stay a little uneven for a while. The County Sanitation district asked for adjustments to the manholes, so concrete collars are going in around the lids. Steel plates will cover those spots during the work, with temporary traffic controls.
The Reopening Order, as the City Lays It Out
The City's project page includes a September 2026 update with a phase-by-phase sequence. Here is where each piece stood as of that update and the October 1 street reopening.
| Piece | Status | Timing per the City |
|---|---|---|
| Open tidal channel | Active | Initial piles removed by week ending Aug. 21; all but one damaged segment out by early September |
| Marina Vista Park | Open, with fencing around active work and new plantings | Reopened July 31; celebrated Aug. 15 |
| Colorado Street and bridge | Open to cars and bikes | Expected Sept. 30; reported open Oct. 1 |
| Decomposed-granite trail segments | Being finished | Segments open in October after punch-list fixes |
| Interpretive signs along the trail | Scheduled | Expected in September and October |
| Sod, native plants, trees, hydroseeding | Soil prep underway | Targeted for October and November |
| Eliot Street | Closed | No date; follows repairs and crews moving out |
Marina Vista Park is the piece already in use. The section returned in August has releveled fields with new irrigation, plus new dugouts, field backdrops and outdoor fitness equipment. Construction fencing is still up around active work. Orange protective fencing will stay around the new plantings while they mature.
The trail matters most for a regular walk. Crews have been compacting decomposed granite and placing site furnishings, along with log-and-wire fencing, picket fencing at the bridges, and split-rail fencing along Colorado Street. The trail between the open channel and Marina Vista Park has its surface material in place. Signs about the lagoon's ecology were expected along it in September and October, and the City says segments will open in October once the punch-list items are fixed. The planting comes after the trail. Soil amendment inside the channel area began in late September, and planting waits until the soil is ready. A walk in mid-October will likely show finished paths running past ground that is still bare.
The Last Loose End Is Near Paoli
Eliot Street is the piece without a date. It runs along the south side of the project, where the channel meets Marine Stadium, and it is still closed. The City has listed what has to happen first. Crews need to finish asphalt repairs near the City's fueling station and fix the concrete bike path at 3rd Street and Paoli, which was damaged when emergency vehicles were rerouted during construction. The field offices, trailers and equipment also have to leave.
That Paoli repair sits close to one of the area's steadiest weekly fixtures. The Marine Stadium Certified Farmers' Market sets up at 5255 E. Paoli Way, near Appian Way and Nieto Avenue, every Wednesday from 3 to 7 p.m., year-round. Through all the construction, the City has kept a note at the top of its project page saying the market remains open on Wednesdays. It has also kept asking drivers to follow the detour signs. Local Harvest Farmers Markets, which runs the market, still lists the Wednesday schedule this fall. On a Wednesday, the walk to the market now passes the newly opened bridge on Colorado Street and ends near the last stretch of work still holding up Eliot.
The water side of Marine Stadium is running normally. The City lists the Marine Stadium launch ramp as open year-round, 8 a.m. to dusk, for boats up to 23 feet, except when permitted events close it. The boathouse entrance at the Pete Archer Rowing Center is listed as open from 5 a.m. to 10 p.m.
The Water Question Is Still Open
The tidal connection is back, and the obvious next question is whether the lagoon is cleaner. Nobody has answered it yet. In early 2025, the City described the natural connection as a way to improve tidal exchange and water quality. No post-activation water-quality results have been published so far.
The useful source for now is the City's recreational water sampling page. It is updated weekly and labels each site as Open, Advisory, Rain Advisory or Closed. The lagoon has two sampling stations, B-24 on the west side and B-25 on the east. Under the City's project FAQ, swimming is allowed only in the lagoon's designated swim area, never in the open channel. That FAQ dates from June 2024, so check the posted signs at the water's edge as well.
Two Saturdays Built Around the Planting Season
The best way to see the restored lagoon up close is the program that has been running here the longest. Friends of Colorado Lagoon runs the Wetlands and Marine Science Education Center, known as WAMSEC, and has offered programs at the lagoon since January 2006. Its Second Saturdays run from 10 a.m. to noon. Each starts with the lagoon's history and ecology and usually includes hands-on planting, weeding or trash removal. Closed-toe shoes that can get dirty are required, and work gloves are welcome.
The next two sessions overlap with the City's planting window.
- Saturday, October 10, 10 a.m. to noon, at WAMSEC. This is the same month the City expects to open the first trail segments.
- Saturday, November 14, 10 a.m. to noon, at WAMSEC. This is near the end of the City's October-to-November target for sod, native plants, trees and hydroseeding.
The group's website points readers to the Third District's weekly newsletter and the City project page for construction updates. You can sign up for automatic project updates on the City page.
In August, Mayor Rex Richardson said he expected the project to be finished "later this year." The City's September update gives no overall finish date. Its cost has also grown since a contractor was chosen in November 2022, from $26.3 million to $32.5 million. Here's what is certain for now. The channel is flowing, Colorado Street is open, Marina Vista Park is in use, and Eliot Street will reopen once the bike path at 3rd Street and Paoli is repaired and the trailers are gone.
Public projects like this one change how a neighborhood works one block at a time, and those changes are part of what we follow for our clients. If you're curious how the reopened lagoon and Colorado Street fit with your own plans in East Long Beach, Heather Dene would be glad to talk it through. Schedule a Private Consultation, and let's look at what's new near you.